D Street to remain open in June
By Jack Kintner
The D Street bridge over highway 543
will be finished and open for traffic in June according
to Patrick Fuller of the Washington State Department of
Transportation (WSDOT). Fuller is assistant project manager
of the extensive $30 million renovation and expansion of
the truck route that began last year.
“Right now the project has been completed on 543
between I-5 exit 275 and H Street,” said Fuller.
Northbound traffic that has been crossing a trucks-only
lane when turning right from the center lane on to H Street
has been redirected to a regular right turn lane.
Signals at the intersection were taken off their permanent
mounts and put up on wires so that they can be shifted
as needed as northbound and southbound traffic is switched
from lane to lane as the work proceeds, and the speed limit
has been reduced to 35 mph.
The design provides three northbound lanes north of H Street,
one of which will be a dedicated trucks-only lane.
The D Street overpass is actually two slab bridges that
meet in the middle where the ramps from the truck route
meet D Street between the north and southbound lanes. The
ramps are roughly the same slope and height that SR 543
was before the work began. The retaining walls are constructed
of 971 drilled shafts that go down as much as 80 feet.
Each shaft slightly overlaps the next one providing the
wall with integrity and strength.
Once the four bridge piers are completed then the slabs
will be poured, D Street will re-open and work will continue
below on 543 as the roadbed is excavated. When complete
the road will be level from H Street to the border, Fuller
said.
Though recent rains left a lot of water on the site, most
of which is being trucked away to either a WSDOT site on
H Street east of Blaine or to a wetlands mitigation site
on Sweet Road, Fuller said that only one spring has been
encountered. “It’s close to the end of 12th
Street,” he said, “but once we drilled below
it at about 30 feet then it wasn’t a problem. All
the rest of the water is simply run-off.”
Officials wait for Drayton
Harbor Road permits
Drayton Harbor Road’s $1 million repair will begin
this summer, “hopefully in July if all the permitting
is done.
“And we anticipate that being accomplished,” said
Whatcom County public works director of engineering Joe
Rutan.
Chris Brueske, the engineer in charge of the project, said
it’s normal to have some uncertainty about permitting
timelines. “It’s too early to say if we’re
off the time line or not. There’s a lot of variability
as to what agencies want,” Brueske said.
For this project they’re working on permits with
the Whatcom County Shorelines and Critical areas staff,
the Washington State Department of Fish and Wildlife, the
Washington State Historical Preservation Office, the U.S.
Army Corps of Engineers, the U.S. Department of Fish and
Wildlife and the National Oceanic and Atmospheric Administration.
In addition to all this they’re also coordinating
with area tribes from a cultural standpoint.
Drayton Harbor was a cornucopia, according to Bellingham
archaeologist Al Reid, and had a native population that
often numbered in the thousands, especially during the
fall salmon runs.