GSA decision slowed by state interchange concerns
Blaine city
officials have been nervous about the negative effect
a new customs facility being built at the Peace Arch
would have on Blaine’s ability to draw southbound
traffic off the freeway. It hasn’t always been easy
to make their voice heard by the General Services Administration
(GSA) but they’ve found an ally in the Washington
State Department of Transportation (WSDOT).
“Here we have the only full interchange on the only
freeway that passes through one of the busiest border crossing
towns in the country,” said WSDOT engineer Todd Carlson. “We
need to keep it working well and to maintain the best possible
access to Blaine,” something the GSA project could
significantly if inadvertently compromise, he continued.
In a January 17 letter, WSDOT’s assistant regional
administrator Todd Harrison pointed out to GSA’s
environmental impact statement (EIS) project manager Michael
Levine that there are problems with the GSA’s proposed
designs that affect traffic flow both on the freeway and
going into Blaine.
In short, none of the three proposed alternatives will
work, not without modifications, or “mitigations” as
Harrison called the changes he’d like to see.
Pressed for space to build the project, the GSA wants to
build on the parts of the highway right-of-way (R/W), giving
the two transportation agencies, WSDOT and the Federal
Highway Administration (FHWA), a kind of trump card over
the project. Their approval depends upon satisfying three
basic conditions: it’s determined that the right-of-way
(R/W) land isn’t needed by the WSDOT in the foreseeable
future, that enough is left in place for WSDOT’s
facility to function properly and that “neither the
federal-aid highway facility nor the traffic thereon” is
adversely affected.
None of these conditions are currently being met, the letter
states, and while Harrison says he’s “hopeful
that our continuing coordination will resolve these issues,
at this time we cannot approve [giving the] R/W [to the
GSA] without mitigation to the transportation system.”
In a meeting last Thursday at the Blaine Senior Center,
the GSA’s project manager Mark Howard, instead of
revealing the GSA’s final choice among three designs
as planned, instead announced a one to two month delay
in their decision due to the concerns raised by WSDOT, “the
most substantial that we have received” on how traffic
flows will be affected by the new facility.
The primary problem is one of getting enough space to construct
the kind of facility that the GSA’s client, the Department
of Homeland Security, wants. The GSA initially sought to
expand the present two-acre site to 15 acres, but constraints
on all four sides of the site have prevented that. Harrison
pointed out that federal law precludes approving “any
project which requires use of any public park,” putting
Peace Arch State Park off limits. The railroad and Semiahmoo
Bay are barriers to the west.
To the east, the GSA still plans to acquire about two square
blocks of residential property, the area west of 2nd Street,
north of C Street, south of Peace Arch State Park
and east of the freeway. Much of last week’s meeting
was devoted to a review of that process.
To the south the GSA is up against an already crowded interchange
276. After reviewing the plans Harrison said they do not “ensure
the functionality of Interstate 5 and access to the city
of Blaine” because they don’t provide enough
room for the exit to work properly unless the whole customs
complex is shifted “approximately 200 feet to the
north. This does not appear to be a viable option for GSA
due to other constraints (most notably Peace Arch State
Park).”
The key seems to be finding a way to fit exit 276 into
the over-all design, something both highway agencies, the
city of Blaine and the GSA are working together to try
to find.
The most likely solution, according to Blaine’s public
works director Steve Banham, would be to change the current
exit 276 configuration by replacing the lighted five-way
intersections where the on- and off-ramps meet D Street
with roundabouts. “The WSDOT loves roundabouts,” said
Blaine city manager Gary Tomsic.
Carlson said that’s because they save money by eliminating
traffic signals, allow more traffic capacity and are safer. “These
are fairly low-speed intersections, but even here when
cars collide it would be at a narrow angle, not a ‘T-bone.’ They
even make it possible to do a u-turn,” Carlson said,
adding that it’s a design solution for this situation
that’s emerged in just the last few weeks. “We
had thought about moving the interchange south, but that
would cost up to $30 million, $5 million more than the
GSA’s cost to build their entire project,” he
said.
WSDOT’s traffic signal operations engineer Pat Armijo
said that the railroad crossing on Marine Drive may make
roundabouts difficult, since “right now we have the
traffic signals set to keep auto and train traffic safely
separated. Roundabouts may not work.” The signals
and controllers at each intersection, he said, are worth
about $150,000.
Banham said a roundabout on Peace Portal Way could also
help delineate Blaine’s Marine Drive, helping it
draw traffic while giving it a more attractive entrance
than the present short stretch of poorly paved road.
Other Problems
Carlson also pointed out that in the three alternate designs
included in the DEIS there’s only room for three
lanes on the bridge that carries the northbound lanes over
the partially buried CBP buildings underneath. “They
need five lanes, including the northbound freeway on-ramp
and the return-to-Canada lane plus two freeway lanes and
the nexus lane,” Carlson said, “and it could
even be a deal-breaker if they can’t do this within
their budget.”
Another local project, the renovation of Highway 543, the
Pacific Highway truck route, is on hold due to appropriated
funds not matching bids that have been submitted, according
to Armijo.
Other problems Harrison cited in the GSA’s EIS include
incompatibilities pertaining to design speeds on the on-ramps
(15 mph) as opposed to that on the freeway itself (45 mph
at that point), not including Blaine and the WSDOT in approving
work zone detour plans while construction is under way
and inadequate consultation with the state historic preservation
officer and local Indian tribes. The report states that
there appears to be “no reporting of archaeological
surveys, no report of walking the site, no shovel test
holes, etc. If this activity was not warranted, please
explain because it appears to not be a fully good faith
effort to follow up on literature work.”
The GSA said at a meeting last December that it had scheduled
the historical and archaeological activities to begin this
month.
Howard said, having seen Harrison’s letter, that
the GSA’s decision to do further studies geared to
the stated concerns does not delay the over-all process,
since they’re not required to identify their design
choice until the EIS is final, though they wanted to make
a choice “as soon as we can so the public has the
benefit of that knowledge as soon as possible.”
Presumably that includes both the WSDOT and the FHWA, as
Carlson pointed out that they’ve had federal funds
in hand for well over a year to begin addressing these
concerns “but we weren’t getting specifics
from the GSA in terms of a footprint, where the thing was
actually going to be built.”
GSA spokesman Bill Lesh was quoted saying the same thing,
that until the January 17 letter the GSA didn’t have
anything to go on from the state officials. Carlson said
that much of this can be chalked up to two different systems
working side by side, “and we’re working together
well now,” he added, “because if we finish
on time that’s still just one month before the Vancouver
Winter Olympics, so the fewer delays we have the better.”
Howard said he’s sticking to the current timetable
that calls for a final EIS to be ready by the end of this
month and published by the end of March. Following a 30-day
public comment period, which Levine inadvertently referred
to as a “cooling off period” at the senior
center meeting, the EIS would become final near the end
of April, leading to condemnation of property where needed
and site preparation for construction to begin next winter.
|
The next informal review of the GSA’s plans is tentatively
set for February 23 at the Blaine Senior Center.