Regional wastewater study to review additional options
By Soren Velice
Although theyve been expecting it for weeks, the feasibility study commissioned by Blaine and the Birch Bay Water and Sewer District to help determine whether or not to merge is still a few weeks over the horizon.
There was some discussion that there needs to be more alternatives for the city, BBWSD general manager Roger Brown said. The study wasnt originally to do that.
Upon review of the draft, city manager Gary Tomsic and public works director Grant Stewart determined the study should examine other options in order to compare alternatives and determine which option is best for the city.
Its
important to have somewhere to turn if things dont
work out, Stewart said. Besides, environmental
review requires you to look at alternatives to make sure
youre doing the right thing, so its environmental
as well as financial. Stewart said other options to
analyze include exporting waste to Canada by way of the
greater Vancouver regional district, building a plant at
Dakota or California Creek or one at the top of Semiahmoo
hill that would use the current discharge at the end of
the spit.
With regard to funding, the feasibility studys main
focus, Brown and Stewart said while the study does describe
ways to seek federal funding for the project, the study
is in too early a stage to release specifics. Theres
no certainty of success, Stewart said, but were
going to beg for some money; Im optimistic
it helps me do my job. Brown said he thought the city
and district would be able to release more information in
early March.
A more concrete move that will increase BBWSDs output is the districts contract with Arco, which purchased a capacity of 30,000 gallons per day. They wouldnt necessarily use it all,Brown said. There could be days theyd use more, and thats addressed in the contract.
He said the capacity will cost Arco $285,510 for the connection, in addition to about $3,140 per month for its share of variable operating costs and a rate of $.9772 per 1,000 gallons, or about $11,000 a year, for treatment. Theyre paying all costs for of construction for improvements and the procedure of the Boundary Review Board incurred for the project, Brown said.