|
More
peaceful waters in harbor,
more room on pier
By
Meg Olson
The
Port of Bellingham will replace the breakwater at the entrance
to Blaine Harbor this summer and in the process more than
double the area open to the public on the pier at the end
of Marine Drive.
Everything on the dock that is Washington Crab will
be gone, said port senior project engineer John Hergesheimer.
The building will be replaced with a portable trailer
and fence the port will bring in October and remove in January.
Failing piles will also be replaced and railings, furniture
and lighting added. It will complete the look thats
there now, Hergesheimer said.
Work on the pier deck will start in July but permits prohibit
in-water work on the pier and the breakwater until July
16. The $2 million project will build a new steel breakwater
outside the existing rotting 60-year-old wooden breakwater
and then pull out all 1,000 piles that make up the old one.
Over six months approximately 150 galvanized steel piles,
from 55 to 200 feet long will be pounded into the mud
the longest ones going down 150 feet. Each pile will have
a sheet of galvanized steel on either side that will link
to the neighboring pile, forming a steel fence on either
side of the harbor entrance. The sheet of steel will end
up to 14 feet above the bottom, Hergesheimer said, to
allow water exchange and creatures to move back and forth.
The opening to Blaine Harbor will be increased by four feet
to 102 feet.
Hergesheimer said the new wave barrier has been designed
to knock six-foot waves expected in a storm only once every
50 years down to two feet. The wave energy hitting
that wall is 3.5 tons per square foot, and it would hit
13 times a minute, Hergesheimer said. Waves from a
ten-year storm would be reduced to one foot.
A promenade along the top of the breakwater connecting both
sides of the harbor was scrapped due to budget constraints,
Hergesheimer said. It wont happen at this time
but the system is equipped to handle it when funds become
available, he said.
In response to concerns about the breakwater segment making
rubbing or banging noises, Hergesheimer said joints between
the panels did have some flexibility to allow it to give
when hit by a powerful wave, but they were too tight to
routinely make noise. He said other designs, such as the
concrete panel breakwater at pier 66 in Seattle, did have
noise problems as concrete panels slid in channels. When
a wave hits, the panels bang in the channel. Ours isnt
like that. Its like the design at Shilshole Marina.
Culbertson Marine, one of the companies that worked on the
expansion of the harbor, has been selected as the contractor
for the job. Theyll start in July and theyll
still be driving piles in November, but it wont be
continuous, Hergesheimer said. Construction plans
are to build the new breakwater in sections outside the
existing structure and remove the old one as those sections
are complete. There will be protection for the harbor
before the old one comes out, Hergesheimer said. The
harbor will remain open to boaters throughout the project,
but there could be some closures of the pier when they are
driving piles beside it.
Hergesheimer said the new breakwater should outlast its
wooden predecessor and is a better environmental choice
than treated wood. With cathodic protection it will
last longer and overall steel is a better choice,
he said.
Back
to Top
|