$30 million city budget for 2002
gets the nod
By
Meg Olson
I
believe, was Blaine city council member John Lieberts
comment on a budget that combines faith and austerity to
float the city through 2002. Faced with little hope of increased
revenues and inexorably increasing costs, the city will
hope for grants and loans to get the big jobs done and take
a red pencil to a score of smaller items.
The bottom line will be the $30 million budget approved
unanimously at the November 26 council meeting 18
percent higher than last years spare budget. The bulk
of the increases are for capital projects, such as sewer
upgrades, funded by grants and loans, many of which havent
been identified yet. The current expense fund, which pays
for city operations from police protection to painting city
hall, will grow less than two percent to $4.6 million.
We identified some key budget issues, not the least
of which was a fairly flat revenue picture, said city
manager Gary Tomsic as budget deliberations entered the
final stretch. City council approved a one-percent property
tax increase at their last meeting, limited to that by the
recent voter approval of initiative 747, which will generate
less than $10,000 for city coffers.
City finance director Meredith Riley said the current economic
climate made an increase in sales tax revenues unlikely
and, in remarks earlier in the meeting, state Senator Georgia
Gardner said cities should not be expecting assistance from
a strapped state government. Dont think for
a minute the state will be able to help you on anything,
she said.
Tomsic stressed the citys expenses had to be trimmed
not only to match revenues but to leave money in the bank.
The budget requests we received drew down the general
fund balance below what we recommend, he said. Our
task became finding a couple hundred thousand to cut.
The street program was one of the hardest hit, with $88,000
earmarked for crack sealing and overlays shaved from its
budget. The program will still have over $100,000 more than
last year, but Tomsic said it isnt enough to keep
up the citys planned 50-year maintenance and improvement
plan. He recommended council form a committee to either
find more dollars or look at lower-cost street maintenance
alternatives.
The longer we delay the further we fall behind,
he said. If we dont come up with additional
dollars we need to cut back on maintenance.
The current expense fund had $228,000 shaved off spending.
That was the one in the most trouble, Riley
said. The savings will boost the funds operating buffer,
set by city policy at 30 days of operating capital.
Spending on the citys computer system was cut by $50,000
and $20,000 in repairs to city hall, including a paint job,
were put on hold.
For a third year were not bringing this building
up to spec or complying with the turn-of-the century guidelines
were asking everyone else to follow, grumbled
mayor Dieter Schugt.
The city is also saving money on personnel costs due to
a decreased need for headhunters, planning consultants and
legal help with labor negotiations.
Tomsic said it was important to focus on what the city was
doing with its money, rather than what it wasnt. Our
budget should reflect our goals and values, he said,
reviewing how the budget moved forward items identified
in the citys strategic plan such as attracting businesses
and tourists to keeping neighborhoods safe. There is ongoing
support for police staffing and continued, though modest,
infrastructure improvement. Projects such as the ongoing
revision of city fees, a loan program to help property owners
spruce up their buildings or lots and planning for a boardwalk
along Peace Portal Drive are funded under the 2002 budget.
Tomsic said running the numbers was only the first part
of a successful budget. Faith in the product was the secret
ingredient. Some people say Ill believe
it when I see it, and then some say Ill
see it when I believe it. I say believe it,
he said.
.
Back