|
Power
crunch may mean cutting projects
By
Meg Olson
Faced
with a substantial jump in the cost of wholesale power as
early as July, Blaine city council is considering its options
to keep the citys electric utility financially viable.
All options include a rate increase for Blaine power customers.
Blaine
has always been able to brag we have the lowest power rates
in the county, said city manager Gary Tomsic at a
March 19 work session. Frankly, theres a question
whether we can maintain that competitive position.
Tomsic said the Bonneville Power Administration, which supplies
100 percent of the citys electricity, was forecasting
a 50 percent increase in the cost of power to the city in
2001/2002. Rates are predicted to jump as much as 300 percent
in five years.
A combination
of dry weather, high power demand in Californias deregulated
market, insufficient production capacity and the rising
price of natural gas were acting to almost guarantee the
current power crunch was not likely to ease up soon.
Tomsic
said while most of the ingredients in Blaines consumer
power rate, such as the cost of raw power and transmission
to Blaines system, were not in councils control,
others were. In 1999 the city issued $4.6 million
in power revenue bonds to be used for capital projects,
Tomsic said. The planned express feeder to west Blaine and
the new Lincoln Road substation tripled the cost of debt
to the utility from 1998 to 2004.
The
express feeder was planned to loop the transmission system
and provide an alternative path for power to get to west
Blaine should the cable under the mouth of the harbor be
damaged. The growth we expected to serve has not materialized,
so its sized large for current demand and should serve
the city well into the future, said public works director
Grant Stewart.
A new
substation at Lincoln Road would increase the citys
capacity to provide power to meet the demand generated from
growth in the area. A regional transmission contract limits
Blaine to a 15.3 megawatt maximum power draw. We hit
that limit once in 1997 but havent come close since,
Stewart said. There are losses associated with having
a substation sitting idle. Until we exceed that limit at
the Blaine substation, the new substation doesnt begin
to pay for itself. Tomsic pointed out that, with construction
almost ready to begin, there could also be some loss associated
with shelving the project. You wont be able
to build it later as cheaply as today, he said
Decisions
were based on scenarios which have changed, based on growth
projections that have been less than forecast, Tomsic
said. He added that costs associated with the two projects
have also increased. Finance manager Meredith Riley estimated
an additional $2.3 million would be needed to complete both.
Stewart
said conservation measures and metering changes could earn
Blaine credits from the state and allow more equitable billing.
One option was credits for residential customers that install
power-saving bulbs. Another was to install meters for big
power users that measure amount of power used in peak and
off-peak hours. The city could charge more for peak consumption,
when they are charged more for the power by BPA, saving
other system users money and encouraging conservation. If
we put new meters on our 50 biggest customers it would monitor
45 percent of our load, Stewart said.
All
of these factors are coming together and forcing you to
make some tough decisions, Tomsic told council members.
You have to balance political on competitive issues
with financial realities.
Options
presented by staff ranged from completing both to neither
of the capital projects, but all included a substantial
rate increase in July and again the following year. Whether
the city proceeds with planned capital projects or not,
the rate hikes for the next two years would be the same,
according to Riley: 34.8 percent in each year if the increase
was levelized or 11 percent in July followed by 58 percent
next year if not. The only difference would come in 2003
if the substation project were continued and additional
money is be borrowed. Continuing with the substation would
mean an additional 6.5 percent hike in 2003 above any increases
associated with the cost of raw power. Riley said shutting
down the express feeder project would have little impact.
Since weve already issued the debt we still
need to pay it back, she said. We could possibly
do an advance repayment and reduce costs, but thats
really not going to change the scenario too much.
I
wouldnt throw out the substation yet, said Frank
Bresnan Jr. Weve exceeded our capacity in the
past and even though growth hasnt happened yet, it
will. Bresnan also pointed out that, while the percentage
increases look significant, its pennies difference
in cost per kilowatt. Blaine now charges 4.9 cents per kilowatt
and Puget Sound Energy charges from 6 to 7 cents. The
kind of increase were talking about would put us in
the same ballpark as Puget Sound Energy.
Dieter
Schugt said he was concerned for community members who would
be hurt by even a modest hike. If we put in a big
rate hike we need to think of what well do for members
of our community who cant afford it, he said.
Hobberlin
said the councils concern needed to be the viability
of the utility. Is the city responsible for the financial
well-being of its citizens? he asked. Do you
run a business based on what your customers can pay?
John
Liebert said the rate increase appeared inevitable, and
would hit ratepayers hard no matter how council decided
to structure it. Its like asking, do you want
to be shot with a rifle or a shotgun, he said. The
people need to be aware that theyve been getting a
break and now its over.
Back
to Top
|