|
City
examines early link to Birch Bay sewers
By
Meg Olson
Anticipating
early approval of the express feeder electrical project
by the Army Corps of Engineers, city staff is looking at
the feasibility of tying in the first steps of regionalizing
sewers.
Suddenly
we have a green light, said Blaine public works director
Grant Stewart at the February 26 Blaine city council meeting.
Were likely to be able to proceed this construction
season with the express feeder project. The project
would run underground electrical transmission lines around
the south end of Drayton Harbor, providing a second pathway
for power to get to Semiahmoo and eventually connecting
the citys old and new substations.
Theres
a great opportunity to go in there and do a sewer project
at the same time, Stewart said. By laying pipe to
connect Blaines life station 5 and the Birch Bay Water
and Sewer District (BBWS) Loomis Trail lift station, the
city would be putting in place a building block of a regional
sewer system prior to working out the feasibility of such
a system. The district and the city are currently reviewing
a working draft of a feasibility study by project consultants
Kennedy/Jenks.
Its
a tremendous opportunity but one fraught with dangers,
Stewart said. The city would save time and money and lessen
impacts by doing the two projects together, but the investment
would be wasted if the regional sewer project didnt
go ahead. At their last meeting city council membersapproved
$10,000 to study alternatives to regionalization, including
sending the sewage for treatment in Canada and building
a new plant for Blaine.
Stewart
said he felt the benefits outweighed the risks. We
minimize the aggravation to the public, the impact on the
environment and we have a better shot at avoiding cultural
conflicts if we put it all in one trench, he said.
The proposal is to lay the sewer line on top of the electrical
duct, which Stewart said has received very positive response
from sewer and electrical project consultants. He said the
city would not only save money and time, but would minimize
permitting requirements and red-tape. Once we have
the right-of-way approved it does make sense to combine
sewer and power and realize the possibility of offloading
some of our capacity to Birch Bay prior to making a decision
about a long-term solution, he said.
The
first phase of the project would only lay sewer line in
the trench with the express feeder duct, but would not connect
to either sewer system or cross the creeks. The link would
only be connected following a feasibility examination in
collaboration with BBWS. Wed have to do some
analysis of our system to see if there would be any bottlenecks
in getting it to the treatment plant, said BBWS manager
Roger Brown. Brown said the BBWS treatment plant had the
capacity to treat up to 200,000 gallons a day from Blaine.
According to Stewart, the option of sending some of the
citys sewage to Birch Bay would relieve pressure on
the citys overburdened sewer. We urgently need
to supplement our capacity, he said, anticipating
it could take five years or more for a long-term solution
to be in place.
City
council directed city manager Gary Tomsic to schedule a
council of the whole meeting in coming weeks to fully review
the proposal. In the interim Stewart said he would study
system flows, determine estimated costs and collect other
information to help council members in their decision. Brown
said the district was willing to work with the city, should
they elect to go ahead with the proposal. Its
probably mostly a question of funding, he said.
Back
to Top
|